Asbestos is still the single biggest cause of work-related deaths in the UK, and it kills decades after the exposure that caused it. So the first rule of any asbestos-related work is the opposite of most jobs: you do nothing until you know what the material is. Before you even think about a method statement, you need a survey and you need to know which category of work you are dealing with, because the most dangerous asbestos work is not something you write your own RAMS for at all. This guide sets out how a RAMS for asbestos work should be approached on a UK site under the Control of Asbestos Regulations 2012.

First, which category of asbestos work is it?

You cannot write a sensible method statement until the material has been identified by a survey and the work has been placed in one of three categories. This is the most important part of the whole job.

A refurbishment and demolition survey to HSG264 is what identifies the asbestos and lets you place the work in the right category. If a material is suspect and has not been surveyed, treat it as asbestos and do not disturb it.

The main hazards of asbestos work

The control measures a reviewer expects (non-licensed and NNLW)

For non-licensed and notifiable non-licensed work, a reviewer looks first for the survey and for confirmation that the work is genuinely non-licensed.

The method statement sequence for non-licensed asbestos work

  1. Obtain the refurbishment and demolition survey and identify the material.
  2. Confirm the work category. If it is licensed work, stop and engage an HSE-licensed contractor. Do not proceed on your own RAMS.
  3. For notifiable non-licensed work, notify the HSE before starting.
  4. Set up the segregated area, restrict access, and prepare RPE, coveralls and waste bags.
  5. Remove the material wet and whole where possible, keeping breakage and dust to a minimum.
  6. Double-bag and label the waste, and clean the area.
  7. Decontaminate operatives and equipment, and carry out any required air clearance before reoccupation.
  8. Consign the waste to a licensed hazardous waste facility and keep the records.

Key point: two rules matter more than anything else. Do not disturb a suspect material until a survey tells you what it is, and licensed asbestos work must be done by an HSE-licensed contractor, not from your own method statement. If you are in any doubt about the material or the category, stop and get it surveyed.

Where asbestos RAMS usually get rejected

Frequently asked questions

Do I need a licence to remove asbestos?

It depends on the material and the work. Higher-risk asbestos such as pipe lagging, sprayed coatings and most asbestos insulating board is licensed work and must be carried out by an HSE-licensed contractor, with notification to the HSE at least 14 days in advance. Lower-risk materials such as asbestos cement and textured coatings are usually non-licensed, but still need trained, competent workers and proper controls.

How do I know if there is asbestos?

You find out with a refurbishment and demolition survey to HSG264 before the work starts. In any building built or refurbished before the year 2000, treat suspect materials as asbestos until a survey or sample proves otherwise, and do not disturb them in the meantime.

Can I remove asbestos myself?

Only lower-risk, non-licensed materials, and only if you are trained and competent with the right controls, RPE and waste route. Licensed asbestos work must go to an HSE-licensed contractor. If you are not sure which category the material is, stop and have it surveyed rather than disturb it.

Is this legal advice?

No. This is a plain-English working summary to support site teams. For the detail see the Control of Asbestos Regulations 2012, and HSE guidance HSG264 for surveys, HSG247 for licensed work and HSG210 for non-licensed work.

New site-safety guides by email

Get our latest toolbox talks, RAMS guides and site-safety updates in your inbox as they land. No noise, just the new guides.

We use your email only to send site-safety guides. Unsubscribe any time.

Get the asbestos-related RAMS right

Site Manager AI produces a task-specific risk assessment and method statement scoped to UK regulations, ready to export as a PDF. For asbestos it helps you record the survey, the category and the controls for non-licensed work, and points you to a licensed contractor where the work is licensed. GBP 9.99 a month.

Get started with Site Manager AI Prefer your phone on site? Download Site Manager AI on the App Store.

Related guides: RAMS for demolition, COSHH assessment for construction, permit to work for construction, and the full RAMS and method statement guides.