RAMS and method statement for hot works

UK construction guidance. Support, not legal advice.

Hot works cause a large share of construction and building fires, and the reason is nearly always the same: heat or a spark reached something combustible, and no one was watching when it took hold an hour later. A risk assessment and method statement for hot works is therefore built around two controls above all others, the permit and the fire watch. This guide sets out what a hot works RAMS should cover on a UK site, whether the task is welding steel, disc cutting, grinding, brazing pipework or torch on felt roofing.

What a RAMS for hot works needs to cover

Be specific about the heat producing task and where it happens. State the type of hot work, welding, cutting, grinding, brazing, soldering, blow torch or bitumen boiler, the exact location, and what is nearby that could catch, from timber and insulation to fuel, dust and the building fabric itself. A weld in an open steel yard is a different risk from cutting inside a finished building or torch on felting a roof over an occupied space, and the document and the permit should reflect the real task.

The main hazards of hot works

The control measures a reviewer expects

Each control should map to a hazard above, and a reviewer looks first for the permit and the fire watch.

The method statement sequence for hot works

  1. Assess the task and issue the hot works permit, confirming the location, the fire watch and the controls.
  2. Clear or protect combustibles, seal voids and gaps, and set up fire resistant screens or blankets.
  3. Position the correct fire extinguishers and brief the fire watch on their role during and after the work.
  4. Check the equipment: flashback arrestors, hoses, leads and insulation, and leak check gas connections.
  5. Carry out the hot work with fume extraction, eye protection and screens in place, keeping the fire watch alert.
  6. Stop the work in good time before the end of the shift so the fire watch period can be completed.
  7. Continue the fire watch for at least 60 minutes, then carry out a final check of the area and any adjacent voids.
  8. Close the permit only once the area is confirmed cool and safe.

Key point: the permit and the fire watch are the controls that actually prevent the fire, and the most dangerous moment is after the work stops. Never allow hot works so late in the day that the 60 minute fire watch cannot be completed before the site is left.

Where hot works RAMS usually get rejected

Frequently asked questions

What is a hot works permit?

A hot works permit is a formal, time-limited authorisation confirming that the fire controls are in place before any welding, cutting, grinding or other heat producing work starts. It names the work, the location and the fire watch, and it is closed out only after the final fire check.

How long must the fire watch continue after hot works?

The fire watch runs throughout the work and for at least 60 minutes after it finishes, with a final check of the area before the permit is closed. This is because heat and hot slag can cause a delayed fire that only takes hold after the work has stopped.

Do I need flashback arrestors on oxy-acetylene?

Yes. Flashback arrestors should be fitted to both the oxygen and the fuel gas lines to stop a flame travelling back into the hose or cylinder. Hoses, regulators and connections are leak checked before use and the cylinders kept upright and secured.

Is this legal advice?

No. This is a plain-English working summary to support site teams. For the detail see the Regulatory Reform (Fire Safety) Order 2005, HSE guidance on welding and hot work, and your insurer's hot work conditions.

New site-safety guides by email

Get our latest toolbox talks, RAMS guides and site-safety updates in your inbox as they land. No noise, just the new guides.

We use your email only to send site-safety guides. Unsubscribe any time.

Do the hot works RAMS in minutes

Site Manager AI produces a task-specific risk assessment and method statement for hot works, sequenced and scoped to UK regulations, ready to export as a PDF. You describe the task and it drafts the permit controls, the fire watch, the hazards and the steps for you to check and adjust. GBP 9.99 a month.

Get started with Site Manager AI Prefer your phone on site? Download Site Manager AI on the App Store.

Related guides: permit to work for construction, RAMS for demolition, COSHH assessment for construction, and the fire safety on construction sites guide.