Most guides tell you what a method statement is. Far fewer show you what a good one actually looks like, section by section, with real wording. This page walks through a complete method statement example for a common UK construction task, explains what each section is doing, and gives you the structure to reuse for any trade.
If you want the background first, our guide to method statements in construction covers the what and the why. This page is the how.
Here is how those sections read for a real task. The wording style matters: plain, specific, and about this site rather than any site.
Project: Single storey rear extension, 14 Elm Road, Reading.
Task: Construction of external cavity wall blockwork and brickwork to damp proof course and above, to wall plate level.
Principal contractor: Example Construction Ltd. Subcontractor: ABC Brickwork Ltd.
Programme: Weeks commencing 19 and 26 October 2026. RAMS ref: ABC-RAMS-041 rev A.
This method statement covers the laying of blockwork and facing brickwork for the extension external walls, including mixing of mortar, loading out of materials, and installation of wall ties, insulation batts, lintels and weep vents. It does not cover scaffold erection or alteration (by others, see scaffold contractor RAMS), excavation, or roof carpentry.
Manual handling of blocks and bricks: blocks over 20kg will not be single person lifted; block grabs and two person lifts used; materials loaded out by telehandler to minimise carry distances.
Work at height above 1.2m: work above shoulder height carried out from the scaffold lift, not from hop ups on the scaffold; scaffold inspected and tagged weekly by the scaffold contractor.
Cement and mortar contact: gauntlets and barrier cream for anyone handling mortar; eye wash station at the mixer.
Silica dust from cutting: blocks cut with a bench saw with water suppression in the designated cutting area; FFP3 masks worn by the operative and anyone within 5 metres.
Telehandler (operator holds CPCS A17), bench saw with water suppression (PAT tested, weekly check sheet), cement mixer, block grabs, hand tools. Materials per specification: 100mm dense concrete blocks, facing bricks, M4 mortar, stainless steel wall ties, cavity insulation batts.
PPE: safety boots, hard hat, hi vis, gauntlets for mortar handling, FFP3 at the cutting station.
Personnel: two bricklayers (NVQ level 2, CSCS), one labourer (CSCS), telehandler operator (CPCS). Supervision by ABC working foreman.
Emergency: first aider on site is the PC site manager; nearest A and E is Royal Berkshire Hospital; assembly point at the site entrance.
Monitoring: this method statement briefed to all operatives before the task starts, briefing register signed and held in the site file; site manager monitors compliance daily; any change in method stops work until this document is revised and rebriefed.
The honest reason method statements end up generic is time. Writing a properly site specific document from a blank page takes an hour or more, and it is an evening job after a long day. AI powered RAMS and method statement generation changes that trade off: describe the task, the site and the conditions in a few lines, and Site Manager AI drafts the full document in UK construction language for you to review, adjust and brief. You stay the competent person; the typing disappears.
Site Manager AI drafts RAMS, method statements and risk assessments from a few notes, in proper UK construction language, ready to review and brief.
Get StartedThe document itself is not named in law, but the duty to plan, manage and communicate safe systems of work under the Health and Safety at Work Act and CDM 2015 is. A method statement is the accepted way to demonstrate that duty, and principal contractors will almost always require one before you start on site.
The risk assessment identifies hazards and controls. The method statement sets out the step by step sequence of the work using those controls. Together they form the RAMS pack, which is why they are usually submitted together.
As long as the task needs and no longer. Two to four pages covers most single trade tasks. A padded document nobody reads is a safety failure dressed as compliance.
Someone who understands the task, usually the contractor doing the work, reviewed by the site or project manager. It must describe how the work will actually be done on this specific site.