RAMS and method statement for lifting operations

UK construction guidance. Support, not legal advice.

Lifting operations go wrong in two main ways: the load falls, or the crane goes over. Both nearly always come back to planning, which is why the law puts a competent person in charge of it. Under LOLER, every lifting operation must be properly planned by a competent person, appropriately supervised, and carried out in a safe manner. A risk assessment and method statement for lifting operations sits alongside the lift plan and shows how the lift will be controlled. This guide sets out what a lifting RAMS should cover on a UK site, whether it is a mobile crane, a telehandler or a tower crane.

What a RAMS for lifting operations needs to cover

Be specific about the lift and the equipment. State what is being lifted and its weight, the lifting equipment and accessories, the lift category from basic to complex, the ground and the environment, and the roles: the appointed person who plans it, the supervisor who controls it, the operator, and the slinger or signaller. A single telehandler lift of a pack of blocks is a different operation from a tandem crane lift of a steel frame, and the document should reflect the real lift.

The main hazards of lifting operations

The control measures a reviewer expects

A lifting reviewer looks first for the lift plan and the appointed person, then for the ground and the capacity.

The method statement sequence for lifting operations

  1. The appointed person produces the lift plan and confirms the lift category.
  2. Check the thorough examination reports for the crane and all accessories are in date.
  3. Assess and prepare the ground, position the crane and set the outriggers on spreader mats.
  4. Establish the exclusion zone and brief the team on the plan and the signals.
  5. The slinger attaches and checks the load, confirming the weight and the rating of the accessories.
  6. Carry out the lift under the supervisor's control, using tag lines to steady the load.
  7. Land and release the load in the set-down area and confirm it is stable.
  8. Stand the crane down, clear the area and complete the records.

Key point: every lift is planned by a competent appointed person before it happens, and no one stands under a suspended load. Poor ground and overloading are the two most common reasons a crane goes over, so check the ground and the duty chart every time.

Where lifting RAMS usually get rejected

Frequently asked questions

What is a lift plan?

A lift plan is the plan produced by a competent appointed person setting out how a lifting operation will be carried out safely: the load, the equipment, the ground, the roles and the method. Under LOLER every lifting operation must be properly planned before it happens.

Who is the appointed person for a lift?

The appointed person is the competent person who plans the lifting operation and takes overall responsibility for it. The role is distinct from the crane supervisor who controls the lift on the day, the operator who works the crane, and the slinger or signaller who attaches and directs the load.

How often is lifting equipment thoroughly examined?

Under LOLER, lifting equipment used to lift people is thoroughly examined at least every 6 months, and other lifting equipment and accessories at least every 12 months, or in line with an examination scheme drawn up by a competent person.

Is this legal advice?

No. This is a plain-English working summary to support site teams. For the detail see the Lifting Operations and Lifting Equipment Regulations 1998, PUWER 1998, and BS 7121, the code of practice for the safe use of cranes.

New site-safety guides by email

Get our latest toolbox talks, RAMS guides and site-safety updates in your inbox as they land. No noise, just the new guides.

We use your email only to send site-safety guides. Unsubscribe any time.

Do the lifting RAMS in minutes

Site Manager AI produces a task-specific risk assessment and method statement for lifting operations, sequenced and scoped to UK regulations, ready to export as a PDF. You describe the lift and it drafts the hazards, the controls, the roles and the sequence for you to check and adjust alongside the lift plan. GBP 9.99 a month.

Get started with Site Manager AI Prefer your phone on site? Download Site Manager AI on the App Store.

Related guides: LOLER 1998 explained, RAMS for excavation and groundworks, RAMS for scaffolding, and the how to write a risk assessment guide.