Risk Assessment Template [2026]

Published: 2026-08-13 Easy to use No sign-up required

A professional, ready-to-use risk assessment template for UK construction. Identify hazards, score the risk with a 5x5 matrix, record your control measures, and check the residual risk.

Purpose

A risk assessment is the legal foundation of safe work on any construction site. Under the Management of Health and Safety at Work Regulations 1999, employers must identify the hazards of a task, decide who might be harmed and how, evaluate the risk, and put suitable control measures in place. On site it usually sits alongside a method statement as part of your RAMS.

This template uses the standard 5x5 approach: score likelihood and severity from 1 to 5, multiply them for a risk rating, apply controls, then re-score the residual risk to confirm it is acceptable.

When to Use This Template

The Template

Risk Assessment

Assessment Reference:[RA-001]
Date of Assessment:[DD/MM/YYYY]
Review Date:[DD/MM/YYYY]
Project / Site:[Enter project name and location]
Activity Assessed:[e.g. Excavation of foundation trench]
Assessed By:[Name, role, qualification]

1. Risk Rating Matrix (Likelihood x Severity)

 Severity 1Severity 2Severity 3Severity 4Severity 5
Likelihood 5510152025
Likelihood 448121620
Likelihood 33691215
Likelihood 2246810
Likelihood 112345

Guide: 1 to 4 Low (green), 5 to 12 Medium (amber), 15 to 25 High (red). Severity 1 = minor first aid, 5 = fatality. Likelihood 1 = very unlikely, 5 = almost certain.

2. Hazard Assessment

HazardWho is at RiskExisting ControlsLSRisk
[e.g. Trench collapse][Operatives, others nearby][Battering / shoring, inspection][2][5][10]
[e.g. Underground services][Operatives][CAT scan, service drawings, safe dig][2][4][8]
[Add rows as needed]     

3. Additional Control Measures

HazardFurther Action RequiredOwnerResidual Risk
[Hazard][e.g. Introduce trench box for depths over 1.2m][Name][4]
    

4. PPE Required

[List the minimum PPE for this activity. E.g. "Hard hat, hi-vis, safety boots, gloves. Eye protection and dust mask when cutting."]

5. Sign-Off

RoleNameSignatureDate
Assessor   
Approved By   

How to Customise This Template

  1. Assess each activity separately, do not combine unrelated tasks in one assessment
  2. Score the risk with existing controls in place, then add further controls and re-score the residual risk
  3. Follow the hierarchy of control: eliminate, substitute, engineering controls, administrative controls, then PPE as a last resort
  4. Name who is at risk specifically, including anyone nearby, visitors, and vulnerable persons
  5. Set a review date and reassess whenever the task, materials or site conditions change
  6. Communicate the findings to everyone involved, a toolbox talk is a good way to do this

Frequently Asked Questions

What is a construction risk assessment?

A construction risk assessment is a documented process that identifies the hazards of a task, decides who might be harmed and how, evaluates the level of risk, and records the control measures needed to reduce that risk to an acceptable level. It is a legal requirement under the Management of Health and Safety at Work Regulations 1999.

How does a 5x5 risk matrix work?

A 5x5 matrix scores likelihood from 1 to 5 and severity from 1 to 5, then multiplies them to give a risk rating out of 25. Ratings are usually banded as low (1 to 4), medium (5 to 12) and high (15 to 25), which tells you how urgently controls are needed.

What is the difference between a risk assessment and a method statement?

A risk assessment identifies hazards and the controls needed. A method statement sets out the step-by-step safe sequence for carrying out the work. Together they form RAMS (Risk Assessment and Method Statement), the standard safety document pairing on UK construction sites.

How often should a risk assessment be reviewed?

A risk assessment should be reviewed whenever the task, materials, plant or site conditions change, after any incident or near miss, and at regular intervals to make sure it stays current. There is no fixed period, but many sites review at least annually or per project phase.

What is residual risk?

Residual risk is the level of risk that remains after all reasonable control measures have been applied. A good risk assessment scores the risk before and after controls to show that the residual risk has been reduced to an acceptable level.

Skip the paperwork. Generate professional risk assessments in seconds.

Site Manager AI creates fully compliant, project-specific risk assessments and RAMS in seconds, so you can spend less time at a desk and more time on site.

Try Site Manager AI

Site Manager AI

Site management tips, straight to your inbox

Practical compliance and site-management guidance for UK construction, plus product updates. Unsubscribe anytime.